Rosebud Lift Station and Lagoon Update June 14, 2021

Rosebud Lift Station Parcon finished installing the electrical work inside the building, installed the fencing around the lift station, completed the gravel access road, and completed the test commissioning for the lift station, which was the final step in construction for the lift station project.  Construction for the lift station is now complete and was […]

Read More

Gleichen 8th Avenue Wastewater Main Replacement Project – Update June 11, 2021

Gleichen 8th Avenue Wastewater Main Replacement Project continued this week, despite some intermittent weather delays.   The contractor has removed and replaced the wastewater manhole at the intersection of 8th Avenue and Greisbach Street.  Removal and replacement of the wastewater services is moving north towards Adams Street, with the entirely of the wastewater main expected to […]

Read More

2021 General Property Assessment Inspections

Wheatland County Assessment department will be performing the 2021 general property assessment inspections for most of the improved parcels located in Range 26(westerly portion of the County) including Hamlets of Carseland, Cheadle and Lyalta (excluding Lakes of Muirfield). The purpose of the inspections is to update property assessment information. The inspections will require taking photographs […]

Read More

Landscaping and Screening Guidelines

Wheatland Council recently approved new Landscaping & Screening Guidelines. There has been concern amongst landowners and the County regarding the impact of development has on the visual quality of the landscape. This resource is intended to provide guidance to landowners, developers or landscape professionals proposing development activities that may need to be approved by the […]

Read More

Notice of Water Pipeline Installation

WID will be performing installation of water pipeline in the following Carseland area locations: The first road bore, located on Twp Rd. 224 between Rge Rd 260 and 261, is scheduled to start on Thursday, June 10, 2021. There will be a reduced speed zone through the work area. The second road bore, located on […]

Read More

Notification of Gas Flaring

North 40 Resources Ltd (N40) is planning to temporarily flare natural gas as part of its routine completion and production operations. This Flaring operation will be in accordance with good oilfield practices as well as Alberta Energy Regulator regulations. Specific information relative to this project is detailed below: Site Supervisor: Gerald Aleman Contact Number: (403) […]

Read More

Driving Awareness Refresh

With summer approaching and more vehicles travelling on the highways, it is important for drivers to remember Speed Limits. In Alberta, the maximum speed limits, unless otherwise posted, are: 50 km/h in an urban area 80 km/h in a rural area including gravel roads 100 km/h on two lane undivided highways 30 km/h in Playground […]

Read More

Notification of Leak Detection Survey

Attention: Landowners within Rockyview Gas Co-op Ltd. Franchise Area Rockyview Gas Co-op Ltd. will be completing a leak detection survey starting on May 31, 2021 and will continue to June 14, 2021. As part of this survey, we will be gathering leak detection data from the low-pressure lines contained within our franchise area. Our contractor, […]

Read More