Rosebud Lift Station and Lagoon Update June 14, 2021
Rosebud Lift Station
Parcon finished installing the electrical work inside the building, installed the fencing around the lift station, completed the gravel access road, and completed the test commissioning for the lift station, which was the final step in construction for the lift station project. Construction for the lift station is now complete and was done ahead of schedule.
Once the Rosebud Lagoon project is complete, the two projects will be connected and will be fully commissioned.
Wheatland County would like to thank Parcon Construction Ltd. for their hard work in completing this project ahead of schedule.

Rosebud Lagoon Update
Knibb Developments Ltd. is continuing earthworks for the Facultative and Storage Cells and have started grading for the discharge line outfall. They have placed riprap around the 500mm culvert at the intersection of the access roads.
Planned activities for the upcoming weeks is to continue the earthworks on the Facultative and Storage Cells. They will also be working on the grading and placement of rip rap for the discharge line outfall to Rosebud Creek as well as installing valves on the forcemain.



Please complete the verification below to continue searching.
Ask your question below, be detailed, our powerful search tool will find answers, links, and references.
Results will appear here when you search...
Please wait, we are getting an answer for you which will appear here along with search results.
Select an option from the left to view available services.