Gleichen 8th Avenue Wastewater Main Replacement Project – Update June 18, 2021

Gleichen 8th Avenue Wastewater Main Replacement Project continued to progress this week.   Removal and replacement of the wastewater services has made it to Adam Street, and will continue north along 8th Avenue, to the west of the Arena.  Next week the contractor will complete the wastewater main replacement on Adam Street and begin the replacement of water and wastewater servicing to the property lines of houses along 8th Avenue.

Wastewater Replacement on 8th Ave
Installing wastewater on 8th Ave