Carseland Fire Hall Update – June 21, 2021
Drywalling is complete and painting has started on the interior. Flooring and ceilings are expected to be completed in the next 2 weeks. The electrical, sanitary and water connections are complete and we are working with ATCO to get the natural gas completed by the end of August. Graveling of the site is in progress […]