Carseland Fire Hall Update – June 21, 2021

Drywalling is complete and painting has started on the interior. Flooring and ceilings are expected to be completed in the next 2 weeks. The  electrical, sanitary and water connections are complete and we are working with ATCO to get the natural gas completed by the end of August. Graveling of the site is in progress and the light poles and car plug ins in the parking lot are being installed. Paving of the parking lot and fire truck accesses is scheduled for next week . The new facility is expected to ready for move in in late September.