Rosebud Lift Station and Lagoon Update July 23, 2021

Rosebud Lift Station

Parcon finished installing the electrical work inside the building, installed the fencing around the lift station, completed the gravel access road, and completed the test commissioning for the lift station, which was the final step in construction for the lift station project.  Construction for the lift station is now complete and was done ahead of schedule.

Once the Rosebud Lagoon project is complete, the two projects will be connected and will be fully commissioned.

Wheatland County would like to thank Parcon Construction Ltd. for their hard work in completing this project ahead of schedule.

Rosebud Lagoon Update

Knibb Developments Ltd. is continuing the earthworks for the Facultative and Storage Cell. For the Storage Cell Knibb’s is currently working on the clay liner for the lagoon bottom which should be completed by the start of next week. Once the base liner is completed Knibb’s will be working on the earthworks for the berms for the Storage Cell. Knibb’s is also starting to install the valves for the forcemain.

Planned activities for the upcoming weeks is to continue with the earthworks for the Storage Cell, installing control manholes for the lagoon and installing the valves on the forcemain.