fbpx
Skip to content Skip to main navigation Skip to footer

Rosebud Lift Station and Lagoon Update August 6, 2021

Rosebud Lift Station

Parcon finished installing the electrical work inside the building, installed the fencing around the lift station, completed the gravel access road, and completed the test commissioning for the lift station, which was the final step in construction for the lift station project.  Construction for the lift station is now complete and was done ahead of schedule.

Once the Rosebud Lagoon project is complete, the two projects will be connected and will be fully commissioned.

Wheatland County would like to thank Parcon Construction Ltd. for their hard work in completing this project ahead of schedule.

Rosebud Lagoon Update

Knibb Developments Ltd. has completed the coconut matting for the outfall for the discharge line.

Planned activities for the upcoming weeks are to continue working on the berms for the storage cell and installing the control level vaults that are required for the lagoons. The crew will also continue installing the forcemain gate valves and air valves.

Back to top