Gleichen 8th Avenue Wastewater Main Replacement Project Construction Start

Schedule Construction crews will commence work on 8th Avenue from Greisbach Street to the cemetery starting Tuesday, May 25th.  Work is anticipated to run until Mid-July, weather permitting. The 8th Avenue Wastewater Main Replacement Project will include: Removal/replacement of wastewater main and service lines up to property lines on 8th Avenue from Greisbach Street to […]

Read More

Rosebud Lift Station and Lagoon Update May 14, 2021

Rosebud Lift Station Parcon finished installing the electrical work inside the building, installed the fencing around the lift station, completed the gravel access road, and completed the test commissioning for the lift station, which was the final step in construction for the lift station project.  Construction for the lift station is now complete and was […]

Read More

Rosebud Lift Station and Lagoon Update May 10, 2021

Rosebud Lift Station Parcon finished installing the electrical work inside the building, installed the fencing around the lift station, completed the gravel access road, and completed the test commissioning for the lift station, which was the final step in construction for the lift station project.  Construction for the lift station is now complete and was […]

Read More

Wheatland Lodge Project Update Meeting May 13, 2021

Join the Wheatland & Area Hospice Society on May 13th at 7 PM on Zoom to hear the latest on the work that has been completed by Berry Architecture + Associates, Wheatland Housing and Management Body, and WAHS. More information here: https://www.wheatlandhospice.ca/newsletters–dccd489a-b0da-4a1c-b61e-49aed355c99b?fbclid=IwAR0HHjQmox3bWNhDv5LNLjFEEjPGZfviNDw5lBbRVaBeUzHUgtyxTyLgR0A

Read More

Rosebud Lift Station and Lagoon Update April 30, 2021

Rosebud Lift Station Parcon has completed the gravel pad around the lift station, installed a gravel access road, placed topsoil and seed, constructed the electrical building, placed a generator on the pad, and began the installation of the electrical components in the electrical building. Next week the contractor will continue to install the electrical boxes […]

Read More

Electronics Expanded Pilot Program

The Drumheller & District Solid Waste Management Association (DDSWMA) has entered a Province-wide competition sponsored by the Alberta Recycling Management Authority (ARMA) for an Expanded Electronics Pilot Program Competition.  The Drumheller Regional Landfill and all transfer stations in Wheatland County are currently accepting additional types of electronics (listed below) as part of the project.  The […]

Read More

Rosebud Lift Station Update April 26, 2021

Parcon has completed the concrete pads for the generator and the electrical building, as well as the backfilling of the lift station tank. During the upcoming week, Parcon plans to install the access road to the lift station, place topsoil, install fencing around the lift station, start framing for the electrical building, and install the […]

Read More

HWY 901 and RR 254 Intersection Upgrades

Construction Period – May 2021 Alberta Transportation and Wheatland County have permitted intersection improvements at the above location to widen the existing intersection to accommodate for acceleration/deceleration lanes. Schedule We anticipate work will start in Early-May 2021 and crews will be working until Late-May 2021, weather permitting, to complete the work. Drivers are expected to […]

Read More