Parcon finished installing the electrical work inside the building, installed the fencing around the lift station, completed the gravel access road, and completed the test commissioning for the lift station, which was the final step in construction for the lift station project. Construction for the lift station is now complete and was done ahead of schedule.
Once the Rosebud Lagoon project is complete, the two projects will be connected and will be fully commissioned.
Wheatland County would like to thank Parcon Construction Ltd. for their hard work in completing this project ahead of schedule.
Rosebud Lagoon Update
Knibb Developments Ltd. is continuing earthworks on the anaerobic cells and the facultative cell. The clay liner has been completed in the two anaerobic cells, as well as the internal access road and the municipal access road.
Planned activities for the upcoming weeks are to continue working on earthworks for the lagoon, installing valves on the forcemain and installing the outfall and rip-rap for the discharge line outfall.
We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.OkPrivacy policy