Rosebud Lift Station and Lagoon Update May 14, 2021
Rosebud Lift Station
Parcon finished installing the electrical work inside the building, installed the fencing around the lift station, completed the gravel access road, and completed the test commissioning for the lift station, which was the final step in construction for the lift station project. Construction for the lift station is now complete and was done ahead of schedule.
Once the Rosebud Lagoon project is complete, the two projects will be connected and will be fully commissioned.
Wheatland County would like to thank Parcon Construction Ltd. for their hard work in completing this project ahead of schedule.

Rosebud Lagoon Update
Knibb Developments Ltd. is continuing earthworks on the anaerobic cells and the facultative cell. The clay liner has been completed in the two anaerobic cells, as well as the internal access road and the municipal access road.
Planned activities for the upcoming weeks are to continue working on earthworks for the lagoon, installing valves on the forcemain and installing the outfall and rip-rap for the discharge line outfall.


sPlease complete the verification below to continue searching.
Ask your question below, be detailed, our powerful search tool will find answers, links, and references.
Results will appear here when you search...
Please wait, we are getting an answer for you which will appear here along with search results.
Select an option from the left to view available services.