Parcon finished installing the electrical work inside the building, installed the fencing around the lift station, completed the gravel access road, and completed the test commissioning for the lift station, which was the final step in construction for the lift station project. Construction for the lift station is now complete and was done ahead of schedule.
Once the Rosebud Lagoon project is complete, the two projects will be connected and will be fully commissioned.
Wheatland County would like to thank Parcon Construction Ltd. for their hard work in completing this project ahead of schedule.
Rosebud Lagoon Update
Knibb Development Ltd. is currently working on the earthworks for the two anaerobic cells and the facultative cell for the Rosebud Lagoon. They are also continuing to install the barbwire fence around the lagoon.
The proof roll for the sub-grade for the access roads has also been completed. Planned activities for the upcoming weeks are to continue with the earthworks for the lagoon berms and clay liner, complete the installation of the outfall and rip-rap for the discharge line, and place and compact pit run and gravel for the access roads to the lagoon.