Carseland Fire Hall Update April 28, 2021

Interior finishing is underway at the fire hall.

The trench drains in the apparatus bays have been formed and drain piping has been installed. Gravel base and vapour barrier preparation is in progress for the concrete floor pour to be completed this week.