Temporary Closure of Township Road 250
Attention Motorists! Township Road 250 between Highway 817 and Range Road 251 from August 10th – 12th. We thank you for your patience!
Attention Motorists! Township Road 250 between Highway 817 and Range Road 251 from August 10th – 12th. We thank you for your patience!
The demolition and removal of various damaged curbs along Railway Ave occurred this week. Currently the contractor is anticipating to be on site next week for the preparation and pouring of these curbs.
Drywalling is complete and painting has started on the interior. Flooring and ceilings are expected to be completed in the next 2 weeks. The electrical, sanitary and water connections are complete and we are working with ATCO to get the natural gas completed by the end of August. Graveling of the site is in progress […]
Sidewalk repairs and construction of the ditch to the west of the arena are now complete. The chip seal installation along 8th Avenue was also finished this week. Finalizing all construction work will be the landscaping repairs, which will be done by Monday, August 9th. Thank you to all residents of Gleichen for your patience […]
Repairs to the cracks in the exterior of the Carseland Water Reservoir has commenced this week with the contractor mobilizing and prepping the south face of the reservoir. Chipping and sealing of exterior cracks on the west elevation will begin next week. Exterior construction work is anticipated to be complete by the end of August.
Rosebud Lift Station Parcon finished installing the electrical work inside the building, installed the fencing around the lift station, completed the gravel access road, and completed the test commissioning for the lift station, which was the final step in construction for the lift station project. Construction for the lift station is now complete and was […]
Sidewalk repairs and construction of the ditch to the west of the arena have commenced this week. Chip seal of 8th Avenue will begin after the long weekend, with landscape rehab to follow. All construction work is anticipated to be complete by the end of next week.
Rosebud Lift Station Parcon finished installing the electrical work inside the building, installed the fencing around the lift station, completed the gravel access road, and completed the test commissioning for the lift station, which was the final step in construction for the lift station project. Construction for the lift station is now complete and was […]
North 40 Resources Ltd (N40) is planning to temporarily flare natural gas as part of its routinecompletion and production operations. This Flaring operation will be in accordance with good oilfieldpractices as well as Alberta Energy Regulator regulations. Specific information relative to this project isdetailed below: Site Supervisor: Gerald Aleman Contact Number: (403) 324-1500 Well Surface […]
North 40 Resources Ltd (N40) is planning to temporarily flare natural gas as part of its routinecompletion and production operations. This Flaring operation will be in accordance with good oilfieldpractices as well as Alberta Energy Regulator regulations. Specific information relative to this project isdetailed below: Site Supervisor: Gerald Aleman Contact Number: (403) 324-1500 Well Surface […]