fbpx
Skip to content Skip to main navigation Skip to footer

Author: Shanna Pierson

Public Notice – Range Road 244 Construction Start

Construction Period – August to September 2021Wheatland County is extending the portion of Range Road 244 north ~1.8km of Township Road 232. ScheduleConstruction is planned to begin the week of August 16, 2021 and crews will be working until Late-September to complete, weather permitting. Range Road 244 Construction will include:• Construction of a 7m wide […]

Read More

Carseland Fire Hall Update – June 21, 2021

Drywalling is complete and painting has started on the interior. Flooring and ceilings are expected to be completed in the next 2 weeks. The  electrical, sanitary and water connections are complete and we are working with ATCO to get the natural gas completed by the end of August. Graveling of the site is in progress […]

Read More

Rosebud Sidewalk Repairs Update – August 6, 2021

Repairs and replacements of the various sidewalks/curbs in Rosebud began late last week.  Sites 1 and 2 (sidewalk and long curb along Martin Ave) were poured early this week, and Site 7 (in front of the Rosebud Hotel) was formed and poured yesterday.  Preparation to Sites 3, 4, and 5 are underway and are expected […]

Read More

Carseland Water Reservoir Repairs Update – August 6, 2021

Repairs to the cracks in the exterior of the Carseland Water Reservoir has commenced this week with the contractor mobilizing and prepping the south face of the reservoir.  Chipping and sealing of exterior cracks on the west elevation will begin next week.  Exterior construction work is anticipated to be complete by the end of August.

Read More

Rosebud Lift Station and Lagoon Update August 6, 2021

Rosebud Lift Station Parcon finished installing the electrical work inside the building, installed the fencing around the lift station, completed the gravel access road, and completed the test commissioning for the lift station, which was the final step in construction for the lift station project.  Construction for the lift station is now complete and was […]

Read More

Rosebud Lift Station and Lagoon Update July 23, 2021

Rosebud Lift Station Parcon finished installing the electrical work inside the building, installed the fencing around the lift station, completed the gravel access road, and completed the test commissioning for the lift station, which was the final step in construction for the lift station project.  Construction for the lift station is now complete and was […]

Read More

Back to top