Carseland Water Reservoir Repairs Update – October 14, 2021
Final water quality test results have passed and the reservoir is going to be back in operation (normal water pressures will resume) Friday, October 15th. We thank you for your patience!
Final water quality test results have passed and the reservoir is going to be back in operation (normal water pressures will resume) Friday, October 15th. We thank you for your patience!
Installation and inspection of all remaining valves on the forcemain is complete. The backfilling of the vaults and piping on all cells is near completion. Loading and pressure testing the forcemain will commence next week, with hydroseeding to follow. Commissioning of the lift station and lagoon is anticipated the week of October 18th.
Curing of the interior coating in the water reservoir is complete and the reservoir has now been re-filled. Wheatland County is waiting on final water quality test results prior to putting the reservoir back in operation, which we are hoping to be early next week. Thank you to the residents of Carseland for your patience […]
Interior coating of the water reservoir was completed this week and will be curing all next week. Outlet pipe repairs will begin next week, with final cleaning and tests to follow.
North 40 Resources Ltd (N40) is planning to temporarily flare natural gas as part of an outage at the third party gas plant that N40’s gas is connected to. This Flaring operation will be in accordance with good oilfield practices as well as Alberta Energy Regulator regulations. Specific information relative to this project is detailed […]
North 40 Resources Ltd (N40) is planning to temporarily flare natural gas as part of an outage at the third party gas plant that N40’s gas is connected to. This Flaring operation will be in accordance with good oilfield practices as well as Alberta Energy Regulator regulations. Specific information relative to this project is detailed […]
Wheatland Wind will be holding a virtual open house on October 31, 2021 at 6:30 P.M. To register for this event, please visit wheatlandwind.com.
Attention Motorists! Range Road 190 between Township Road 262 and Township Road 263 will be closed September 21st to 30th for culvert replacement. We thank you for your patience!
Exterior crack repairs and painting of the reservoir is now complete. Interior works commenced this week and is expected to continue into the following week.
Last week Knibb Developments Ltd. worked on backfilling the vaults and piping, they also installed five air valves and one gate valve on the forcemain. This week they will continue to install the remaining five air valves and one gate valve on the forcemain. Knibb’s will also be completing the backfilling for the vaults and […]