Installation and inspection of all remaining valves on the forcemain is complete. The backfilling of the vaults and piping on all cells is near completion.
Loading and pressure testing the forcemain will commence next week, with hydroseeding to follow. Commissioning of the lift station and lagoon is anticipated the week of October 18th.