Carseland Cole Crescent Update: July 28, 2023
The contractor successfully completed all remaining concrete work this week. However, due to the necessary curing times and inclement weather, the granular base installation for the road has been postponed until Monday, July 31st, weather permitting. The paving of Cole Crescent is still scheduled to be completed by the end of next week.
Please continue to exercise caution and follow all posted signage and closures in the area.