fbpx
Skip to content Skip to main navigation Skip to footer

Carseland Cole Crescent Update: July 21, 2023

Concrete sidewalks, curb, and gutter were poured the week of July 10th. During this past week, the mandatory curing period for the concrete was completed, along with the final grading adjustments.

Weather permitting, the contractor is expected to finish all remaining concrete pours early next week. Granular base for the road will follow, and asphalt paving is anticipated for the week of July 31st

Please continue to exercise caution and follow all posted signage and closures in the area.

Back to top