Environmental Appeals Board – Notice of Hearing

RE: EarthRenew Strathmore Inc./Water Act Licence No. 00433625-00-00/Our File Nos.: EAB 20-026 Water Act Licence The Environmental Appeals Board has scheduled a hearing for July 15, 2021 to hear submissions with respect to the September 22, 2020 decision of the Director, South Saskatchewan Region, Alberta Environment and Parks, to issue Water Act Licence No. 00433625-00-00 […]

Read More

Rosebud Lift Station and Lagoon Update May 10, 2021

Rosebud Lift Station Parcon finished installing the electrical work inside the building, installed the fencing around the lift station, completed the gravel access road, and completed the test commissioning for the lift station, which was the final step in construction for the lift station project.  Construction for the lift station is now complete and was […]