Rosebud Additional Water Main Update: October 21, 2022

Water pipe installation has progressed in Rosebud this week, with over 410m placed.  Installation and connections will continue westward up the hill, with the final east portion near the fire hall expected to commence next week. 

Please exercise caution and follow all posted signage if you are in the area.

Thank you to all residents for your patience and cooperation with the Rosebud water main project.