Rosebud Lagoon Update September 16, 2021
Last week Knibb Developments Ltd. worked on backfilling the vaults and piping, they also installed five air valves and one gate valve on the forcemain. This week they will continue to install the remaining five air valves and one gate valve on the forcemain. Knibb’s will also be completing the backfilling for the vaults and […]