Carseland Construction Notice – Cole Crescent Repairs

Construction Period – May 2023 to July 2023

Wheatland County is doing sanitary line repairs and reconstruction of Cole Crescent asphalt, sidewalks, and curb/gutter.

Schedule

Construction is planned to begin as weather permits the week of May 1st, 2023 and crews are anticipated be working until early July 2023.

Cole Crescent Repairs will include:

  • Sanitary line replacement
  • Fire hydrant replacement and relocation (temporary water service required)
  • Sidewalk, curb and gutter replacement
  • Road reconstruction and paving
  • Impacted driveway sectional replacement

Traffic Impacts

Cole Crescent will be closed to all vehicle and pedestrian traffic during construction.  Residential parking and access to properties will remain available via alleys.  Signage will be posted in advance to allow ample time for residents to relocate all vehicles from Cole Crescent.  Emergency access will remain available throughout the duration of the project. 

Construction Updates

Once construction commences, weekly updates will be posted on the County website: www.wheatlandcounty.ca

The contractor will reach out directly to property owners to review and coordinate specific interruptions of service or other project related details as required.

Back to top

What information or resources are you looking for?

NEED ANSWERS QUICKLY?

Ask your question below, be detailed, our powerful search tool will find answers, links, and references.

I'D LIKE TO...

APPLY FOR +
FIND +
HOW DO I? +
REPORT +

Select an option from the left to view available services.