Rosebud Lagoon Update September 16, 2021

Last week Knibb Developments Ltd. worked on backfilling the vaults and piping, they also installed five air valves and one gate valve on the forcemain. This week they will continue to install the remaining five air valves and one gate valve on the forcemain. Knibb’s will also be completing the backfilling for the vaults and piping that are located in the Anaerobic cell, Facultative Cell and Storage Cell.

For the next couple of weeks, Knibb’s will be installing the flow meter in the Storage cell and placing the rip rap armoring that is required for the top of berms for all the lagoon cells.