Operation | Duration (days) | Start Date (estimated) | Completion Date (estimated) |
Fencing | 14 | May 8 | May 26 |
Street Lighting | 15 | May 8 | May 26 |
Erosion Control | 14 | May 26 | June 8 |
Cold Milling | 2 | June 1 | June 2 |
Grading | 8 | June 1 | June 8 |
Gravel Prep | 5 | June 1 | June 5 |
Paving | 12 | June 1 | June 15 |
Painting | 2 | June 15 | June 16 |
Rumble Strips | 5 | June 17 | June 21 |
Signs/Guardrail/Delineation | 3 | June 13 | June 15 |
Schedules are subject to change based on weather, fatigue management and equipment breakdowns. Notices will be posted on 511 Alberta (https://511.alberta.ca), while the Contractor will employ variable message boards to notify motorists of work zones.
The highway will remain open throughout the remainder of construction operations, as the Contractor will employ one-lane alternating closures when workers are present on the highway surface.
Please avoid foot traffic within the project limits.
We ask for local residents’ patience and understanding as there may be traffic delays and increased levels of noise and dust during construction.
Thank you for your cooperation and patience.