OperationDuration (days)Start Date (estimated)Completion Date (estimated)
Fencing14May 8May 26
Street Lighting15May 8May 26
Erosion Control14May 26June 8
Cold Milling2June 1June 2
Grading8June 1June 8
Gravel Prep5June 1June 5
Paving12June 1June 15
Painting2June 15June 16
Rumble Strips5June 17June 21
Signs/Guardrail/Delineation3June 13June 15

Schedules are subject to change based on weather, fatigue management and equipment breakdowns. Notices will be posted on 511 Alberta (https://511.alberta.ca), while the Contractor will employ variable message boards to notify motorists of work zones.

The highway will remain open throughout the remainder of construction operations, as the Contractor will employ one-lane alternating closures when workers are present on the highway surface.

Please avoid foot traffic within the project limits.

We ask for local residents’ patience and understanding as there may be traffic delays and increased levels of noise and dust during construction.

Thank you for your cooperation and patience.

Back to top