Range Road 243 Paving & HWY 1 Acceleration Lane Update: July 12, 2023

Road structure works including subgrade preparation and granular base course has been ongoing this past week and will continue to the end of this week.  Weather permitting, the contractor is expected to be paving early next week and is aiming to be wrapped up by July 23rd. 

Please continue to exercise caution and follow all flagging, posted signage and closures in the area.