Alberta Transportation Paving Notification
Attention Motorists! Alberta Transportation will be conducting road slope repair and repaving of HWY 561 from HWY 1 to HWY 56, from July 22 – Sept 3.
Attention Motorists! Alberta Transportation will be conducting road slope repair and repaving of HWY 561 from HWY 1 to HWY 56, from July 22 – Sept 3.
Construction Period –Summer/Fall 2021 The water reservoir in Carseland is over 50 years old and due to its age, has been showing signs of leaking. To prolong the longevity of the system, several repairs are required. ScheduleExterior work will start in Late-July and crews will be working until Late-August to complete the work. Interior repairs […]
Road coring is complete for the Gleichen 8th Avenue Wastewater Main Replacement Project. The contractor is now placing gravels along 8th Ave and Adam Street, and chip seal will be placed on the road next week. Repairs to the sidewalks and landscaping will follow.
The contractor has now completed the replacement of all water and wastewater services to the property lines of houses along 8th Avenue. As a result of the wet weather, the start of road works has been delayed, with coring and subgrade prep expected to commence next week.
Date: July 19-26Time: 8:00 a.m. to 6:00 p.m.Location: Launcher – SE 6-25-19 W4M Receiver – SE 24-20-4 W4M A blowdown is the act of releasing natural gas from the pipeline system so work can be done safely on the depressurized facilities. TC Energy employees will close the required valves to isolate the facilities and then […]
The contractor has begun the replacement of water and wastewater services to the property lines of houses along 8th Avenue. This work is anticipated to run to mid-next week, with road works to follow immediately afterwards.
Gleichen 8th Avenue Wastewater Main Replacement Project reached a significant milestone this week. Removal and replacement of the wastewater main is now complete. For the next week and a half, the contractor will begin the replacement of water and wastewater services to the property lines of houses along 8th Avenue.
CN will be onsite to remove the rail crossing on Range Road 264, south of Lyalta and Lakes of Muirfield, on Wednesday June 23rd. County forces will be closing Range Road 264 at 10am on either side of the crossing at the intersections of Township Road 250 and Township Road 251A. The closure will extend […]
Gleichen 8th Avenue Wastewater Main Replacement Project continued to progress this week. Removal and replacement of the wastewater services has made it to Adam Street, and will continue north along 8th Avenue, to the west of the Arena. Next week the contractor will complete the wastewater main replacement on Adam Street and begin the replacement […]
Gleichen 8th Avenue Wastewater Main Replacement Project continued this week, despite some intermittent weather delays. The contractor has removed and replaced the wastewater manhole at the intersection of 8th Avenue and Greisbach Street. Removal and replacement of the wastewater services is moving north towards Adams Street, with the entirely of the wastewater main expected to […]