Carseland Water Reservoir Repairs Update – August 13, 2021

Repairs to the cracks in the exterior of the Carseland Water Reservoir has continued this week with the contractor completing the crack repairs on the south face of the reservoir.  The chipping and sealing of exterior cracks on the west elevation has commenced, and will continue into next week.