Rosebud Lagoon Update October 25, 2021
Last week, the contractor was placing and backfilling manholes and valves required for the discharge line, and completed the installation of the access gate for the lagoons. Placement of topsoil on the berms of the lagoon cells and pressure testing the forcemain was ongoing.
Final project touch-ups and commissioning is scheduled for this week, with all works expected to be complete by month end.