Range Road 205 Construction Update – May 2, 2022

Last week the contractor mobilized the site and completed stripping in Phase 1 (north end of RR 205).  This week will be focused on grading Phase 1 and centerline culvert installations.

Please follow all detours and posted signage if you are driving in the area.