Carseland Fire Hall Work Update
- Piling and foundations have been completed and concrete is curing in preparation for the building.
- The pre-engineered building is being delivered at the end of January and will take 6 weeks to erect the building. Once complete interior finishing of the building will start.
- Fortis Alberta is in the process of installing power to the site. New poles have been installed and will be directionally drilling the service under the road to the site.