Carseland Fire Hall Work Update

  • Piling and foundations have been completed and concrete is curing in preparation for the building.
  • The pre-engineered building is being delivered at the end of January and will take 6 weeks to erect the building. Once complete interior finishing of the building will start.
  • Fortis Alberta is in the process of installing power to the site. New poles have been installed and will be directionally drilling the service under the road to the site.