Carseland Fire Hall Update – March 10, 2021

With the building almost enclosed, the process of thawing the ground inside the building has begun using glycol heating tubes and insulated tarps.

It is anticipated that this process will take approximately 2 weeks, after which excavation and installation of underground plumbing will commence. Final measurements for all the doors and windows have been taken and those items are now in fabrication.