fbpx
Skip to content Skip to main navigation Skip to footer

Carseland Fire Hall Update – Feb. 25, 2021

The building is continuing to take shape and showing off the classic white and red colours of a Fire Station. 

Despite the cold weather, we are still on track to getting the building enclosed and the overhead doors installed by the middle of March. Once enclosed, the ground thaw will begin to prepare for the installation of the plumbing and floor slab.

Back to top