April 15, 2021, Carseland Fire Hall Update
The Building exterior shell is now finished except for windows and doors. The thawing of the ground inside the building is completed and installation of the under slab plumbing and electrical is in progress. The apparatus bay trench drain bases have been formed and are being poured this week. Gravel and slab preparation will start next week.
Overall the Project continues to track on schedule and budget.